Process

How a Northbrook home addition proceeds.

Design and permitting often take longer than framing. We say so at the first meeting. A second-story schedule that ignores village review is not a schedule we will sign.

Occupied North Shore house during a rear home addition, with site fencing and the family still living in the front
  1. 01

    Site visit

    60–90 minutes

    The principal walks the house with you: structure, electrical service, drainage, setbacks, and how the family lives in the rooms. We will say whether the addition belongs on the lot.

  2. 02

    Feasibility

    1–2 weeks

    A short letter covering what the lot and the village will allow, with an indicative planning range. There is no obligation to sign a construction contract at the site visit.

  3. 03

    Design team

    4–10 weeks

    Your architect, or an introduction to a North Shore firm. Schematic design, structure, and a budget with allowances.

  4. 04

    Village review

    4–12 weeks

    Permits, design review, stormwater, and variations if required. We pull them as contractor of record. Design and permitting often take longer than framing.

  5. 05

    Construction

    4–8 months

    Site protection, a weekly written update, one point of contact. Most families remain in the house.

  6. 06

    Closeout

    2–3 weeks

    Punch list, written workmanship warranty, and photographed completion. Warranty items are scheduled promptly, not deferred.

We build with your architect. If you do not have one, we introduce a North Shore firm we already work with. Sealed drawings are required for second-story work. In Northbrook we register as contractor of record before we bid.

Questions about the addition process

Can we remain in the house during a North Shore addition?
On most additions, yes. Occupied-residence protocol is the default: site protection, a weekly written update, and a single point of contact. You will know in advance the day water or power must be interrupted.
How much does a home addition cost on Chicago’s North Shore?
Indicative ranges, not bids: family rooms often $200,000–$350,000+, primary suites $250,000–$450,000+, second stories $350,000–$600,000+. A written proposal follows the complimentary site visit.
Do you have an architect on staff?
Not at present. We build with your architect, or we introduce a North Shore firm we already work with. Sealed drawings are required for second-story work.
What does a project review cost?
The site visit is complimentary. If the project belongs with this practice, a short feasibility letter follows. There is no obligation to sign a construction contract at the walk.
Which North Shore villages do you serve?
The office is in Northbrook. The practice is limited to North Shore villages — Northbrook through Lake Forest, including Winnetka, Glencoe, Highland Park, Wilmette, Kenilworth, Glenview, Northfield, and Deerfield. We do not work in the City of Chicago.
How long does a North Shore home addition take?
Design and permitting often take longer than framing. Construction is typically four to eight months after permits are issued. A second story promised for the coming season, without drawings, is not a schedule we will sign.

Arrange a site visit

Share the village, the type of work, and an indicative budget. We review the house before we discuss numbers.